Update: June 26, 2019 at 10:57 AM
The construction fencing started going up this morning. We will have access to the front parking for a limited number of days until this gate will only be used by JAXI construction. Temporary fencing is also going up along the campus that will be moved around as they start the trenching process for the storm […]
Equality Park – Big tree trunks removal – Parking space blocked
Parking area highlighted in green will be blocked tomorrow for at least 4 hours to remove all the big tree trunks as a result of the tree disposition work, expect a flatbed truck and a grapple service. This activity will start at 8:00am. Robert Boo, CEO
The Residences at Equality Park
Great news! We have received the construction permits from both the County and the City of Wilton Manors and then yesterday, Carrfour completed the financial closing with Florida Housing Authority. We will start seeing movement on the campus starting next week at some point. Robert Boo, CEO